Proposed Activities
The HEC-RAS team is focused on the development of the next generation of HEC-RAS (version 7.0). Because of that effort, the focus of this year's activities include development of a 3-year plan for the integration of the new version of HEC-RAS into the CAVI. The team will continue to provide field support to the water management community on an as-needed basis.
Other efforts will focus on finalizing enhancements that will allow modelers to link results from HEC-RAS in HEC-FIA using HDF files. This will be completed once HEC-RAS 6.5 is released later in FY24.
Activity | Funded (Y/N) | Cost |
---|
Linking Results in HEC-FIA with HDF files (HEC-RAS 6.5, CWMS 3.4.0) | Y | $15,000 (HEC labor) |
Bug Fixes and Testing (CWMS 3.4.0) | Y | $45,000 (HEC labor) |
Technology Transfer (Working Sessions, Field Support) | Y | $65,000 (HEC labor) |
Plan for Integration of HEC-RAS 7.0 within the CAVI | Y | $100,000 (HEC labor) |