Download page Appendix A Folio Schedule Milestones.
Appendix A Folio Schedule Milestones
Project
Activity Name
Activity Description
Current Baseline
Total Cost ($1000)
Start Date
End Date
Planned
Actual
Planned
Actual
Planned
Actual
FY24 CWMS Feature Enhancements
Release CWMS 3.4
Release a new version of CWMS (version 3.4) with software bug fixes and minor enhancements
$1,116.000
10/1/2023
10/1/2023
09/30/2024
FY24 Cyber Security
Cyber Security Activities
Timely address vulnerabilities identified in ACAS scans, review and update artifacts in the CWMS eMASS record, ensure enhancements are compliant with cyber security requirements, and continue to monitor STIGs and create POA&Ms if non-compliant.
$387.000
10/1/2023
10/1/2023
09/30/2024
FY24 Maintenance (Operations)
Maintenance Activities
Maintenance activities include CWMS helpdesk, software bug fixes, database schema updates, quarterly patch testing, database and operating system support, updates to comply with database policy and CCRI directives, CAC authentication updates, App Portal compatibility and support to 36 USACE District/Division Water Management offices.