Appendix A Folio Schedule Milestones
Project
Activity Name
Activity Description
Current Baseline
Total Cost ($1000)
Start Date
End Date
Planned
Actual
Planned
Actual
Planned
Actual
CWMS
CWMS WM Modeling and Decision Support
Provide SMEs to national modeling teams for software model applications and training to the 36 USACE water management offices to support policy objectives regarding annual reporting of flood damages reduced, real-time inundation maps, and training.
$2,600
CWMS
CWMS Modernization
These developments are to support evolving technology and to meet standards and expectations of the water managers and mission requirements.
$5,165
CWMS
CWMS Features Enhancements
Model enhancements to include flood damages reduced support for 2D HEC-RAS, gridded data editor, ensemble capabilities improvements, vertical datum, OSI enhancements, HEC-DSS version 7 compatibility with all models, and improved automation.
$6,390
WMES
WMES Data Tools
Provide support and enhance the USACE enterprise data collection systems and activities such as LDM, NOAA and OpenDCS (critical activities to ensure timely and accurate data sharing with our partners and maintain consistency across USACE districts).
$7,800
WMES
WMES Cloud Migration and Enhancements
Implement web-based approaches, such as exploration of “cloud-native” functionality to leverage one-stop deployment, load balancing, fail-over server/database access, distributed computing, etc.