Planned Activities

Most of the planned activities in FY24 support cloud migration efforts. The team plans to migrate Goldengate off of the processing centers and onto the CWBI testing/production sites this FY. Work will also be completed to ingest USGS and LDM data into the national database. Also, the current build system will be migrated to Flyway and Gradle to support cloud migration efforts. 

The team will continually monitor performance of the database and improve as needed, based on feedback from the field. 


ActivityFunded (Y/N)Cost
Minor improvements and user supportY$25,000 (HEC labor)
Cloud Migration - Migrate Goldengate to CWBI testing/productionY$15,000 (HEC labor)
Cloud Migration - Data Acquisition and National Database Administration Y

$134,000 (HEC labor) 

$50,000 (field labor)

Monitor Performance and Improve as neededY

$36,000 (HEC labor)

$20,000 (Field labor)

Authentication of Public vs Private DataY

$10,000 (HEC labor)

$50,000 (HEC/Field labor)

Versioning of Ensemble DataY

$2,500 (HEC labor)

$25,000 (contract)

Cloud Migration - Migration of Historic Public Data into CWBIY

$10,000 (HEC labor)

Cloud Migration - Move Current Build System to Flyway & GradleY

$80,000 (HEC labor)