Background for Flood Risk Management Studies
Flood-frequency functions developed following procedures described in the Flood Frequency Studies provide quantitative information about the risk of flooding in a watershed. If the flow-frequency functions are combined with rating and stage-damage information, expected annual damage (EAD) can be computed. This computation is the foundation for assessment and comparison of the effectiveness of flood risk management plans. This chapter illustrates how HEC-HMS can be used in the context of such a study.
Authority and Procedural Guidance
USACE activities in flood risk management studies are authorized by:
- The Flood Control Act of 1936.
- Section 206 of the Flood Control Act of 1960.
- Executive Order 11988.
- Section 73 of Public Law 93-251.
Flood risk management (FRM) studies were formerly referred to as flood-damage reduction or flood-loss reduction studies, and some of the guidance cited below uses that terminology. In addition to technical guidance identified in earlier chapters, relevant USACE guidance for hydrologic engineering analyses in FRM studies includes:
- EP 1110-2-10 (USACE, 1994) provides an overview of flood-damage reduction studies and describes the basic principles of the analyses required throughout a study. It addresses the role of various computer programs in those analyses.
- EM 1110-2-1419 (USACE, 1995) identifies possible damage reduction measures and summarizes typical hydrologic engineering studies required for formulation and evaluation of each.
- EM 1110-2-1619 (USACE, 2025) describes risk assessment procedures for flood risk management studies, including how uncertainty in the flow-frequency function is described. It supersedes the 1996 edition used in the case study in this chapter and incorporates the guidance formerly published as EP 1110-2-9.
- ER 1105-2-101 (USACE, 2019) establishes the risk assessment requirements for flood risk management studies.
- ECB 2026-1 (USACE, 2026) requires an assessment of long-term hydrometeorological conditions for studies that rely on flow-frequency or stage-frequency relationships, such as those developed with HEC-HMS in this chapter. The bulletin expires 9 January 2028.
Study Objectives
Flood risk management studies are typically undertaken to find the optimal plan to reduce flood damage for a particular watershed - in this case, the optimal plan is the plan that yields the maximum net benefit. In addition to economic damage, current risk assessment guidance addresses life safety; EM 1110-2-1619 (USACE, 2025), Chapter 11, describes methods for understanding and estimating potential life loss. As described in EM 1110-2-1419 (USACE, 1995), net benefit, NB, of a proposed plan is computed as:
NB = B_{L}+B_{I}+ \big(E[D_{without}]-E[D_{with}]\big)-C
where:
BL= annual equivalent location benefit of the plan;
BI = annual equivalent intensification benefit of the plan;
E[Dwithout]=EAD in the watershed without the plan;
E[Dwith]= EAD with the plan in place;
C= annual equivalent cost of implementing, operating, maintaining, repairing, replacing, and rehabilitating all components of the plan.
The without-project condition represents existing and future conditions in the absence of the plan, and the with-project condition represents conditions if a damage reduction plan is implemented.
EM 1110-2-1415 (USACE, 1993) describes how the EAD for an urban area, both without and with a plan, is computed by integrating the appropriate annual damage-frequency function. The flow-frequency function is transformed with a rating curve (relationship of flow and stage), thus yielding a stage-frequency function. This, in turn, is transformed with a stage-damage function, yielding the required damage-frequency function.
The flow-frequency, flow-stage, and stage-damage functions used in the EAD computation are not known with certainty. For example:
- Uncertainty about future hydrologic events and watershed conditions, uncertainty regarding the choice of a statistical distribution, and uncertainty regarding values of parameters of the distribution lead to uncertainty about the frequency function.
- Uncertainty that arises from the use of simplified models to describe complex hydraulic phenomena, from the lack of detailed geometric data, from misalignment of a hydraulic structure, from material variability, and from errors in estimating slope and roughness factors leads to uncertainty about the rating function.
- Economic and social uncertainties, including lack of information about the relationship between depth and inundation damage, lack of accuracy in estimating structure values and locations, and lack of ability to predict how the public will respond to a flood, cause uncertainty about the stage-damage function.
- Uncertainty about structural and geotechnical performance of water-control measures when these are subjected to rare stresses and loads caused by floods, cause further uncertainty about flood elevations.
Historically in USACE planning studies, these uncertainties were not considered explicitly in plan formulation and evaluation. Instead, the uncertainties were accounted for implicitly with factors of safety and freeboard. Beginning with the 1996 edition of EM 1110-2-1619, USACE guidance has called for explicit acknowledgement and description of uncertainties and for quantitative risk analysis in the EAD computation; current requirements are in ER 1105-2-101 (USACE, 2019) and EM 1110-2-1619 (USACE, 2025). In simple terms, a description of uncertainty in each of the functions is included in the transformation and integration. Such a distribution might reveal, for example, that the probability is 0.05 that the error in predicting the 0.01 probability discharge is greater than 500 cfs.
With such a description of the error or uncertainty, a description of the uncertainty of the EAD value can also be derived, reported, and weighed in the decision making.
The following table lists damage reduction measures, both structural and nonstructural, and shows how each will alter the frequency, rating, or damage function. Complex plans that include multiple measures will alter more than one of the functions. EM 1110-2-1619 (USACE, 2025) provides risk assessment guidance for specific measure types: levee and floodwall systems (Chapter 6), reservoirs and diversions (Chapter 7), channel modifications (Chapter 8), and nonstructural measures (Chapter 9). The impact of measures that alter the frequency function can be evaluated conveniently with HEC-HMS. Evaluation of the impacts of others may require use of other software that is listed in the Other HEC Software that can be used Along with HEC-HMS to Perform a Hydrologic Analysis table.
Damage Reduction Measures and their Impact
Measures that Reduce | Measures that Reduce | Measures that Reduce |
|---|---|---|
Reservoir/detention | Channel improvement | Relocation of property (temporary or permanent) |
Representation in HEC-HMS: modeled directly, using the reservoir element (detention), the diversion element, and subbasin parameters that reflect watershed conditions (watershed management). | Representation in HEC-HMS: changes in stage are computed with a hydraulic model, such as HEC-RAS. HEC-HMS reach routing (for example, Muskingum-Cunge cross sections) can represent changes in floodplain storage that affect downstream flows. | Representation in HEC-HMS: not represented; these measures change the stage-damage relationship used in the economic analysis, such as HEC-FDA. HEC-HMS can support related analyses, as described in Flood Warning System Planning Studies. |
Study Procedure
The study procedure is straightforward:
- Develop the without-project flow-frequency function, including a description of the uncertainty. HEC-HMS may be used to develop the function.
- Combine that frequency function with the without-project rating and damage functions, which are also known without certainty. Computer program HEC-FDA can be used for this combination and computation.
- Select one of the proposed plans and develop the with-project frequency function for that condition, including a description of the uncertainty.
- Combine that frequency function with the with-project rating and damage functions and compute the with-project damage frequency function, including a description of uncertainty, and EAD for the plan.
- Determine intensification and location benefits, the cost of the plan, and the net benefit.
- Compute other measures of system performance, such as annual exceedance probability (AEP), long-term exceedance probability (LTEP), and assurance, following guidance in EM 1110-2-1619 (USACE, 2025).
- Repeat Steps 3, 4, 5, and 6 for all other proposed plans.
- Compare the results to select the optimal plan.
Current versions of HEC-HMS include compute types that support several of these steps. The Frequency Analysis compute type, available beginning with HEC-HMS version 4.10, combines a set of frequency events into a single compute and produces a flow-frequency curve (or a stage-frequency curve, if a rating curve is available) at a selected element, which supports Steps 1 and 3. The Uncertainty Analysis compute type samples model inputs from specified distributions, including basin parameters and, for hypothetical storms, precipitation depth, temporal pattern, and area reduction, to evaluate how variability in those inputs affects computed flows. The description of frequency-function uncertainty used in the EAD computation should still follow EM 1110-2-1619 (USACE, 2025), Chapter 3.
Note that these steps require significant interaction amongst members of the study team: hydrologic and hydraulic engineers will provide the frequency functions, economists will provide the stage-damage information, and cost estimators will provide costs of construction.