Summary for Reservoir Spillway Capacity Studies
Summary
This chapter illustrates a probable maximum flood (PMF) evaluation, in which HEC-HMS converts probable maximum precipitation (PMP) into an inflow hydrograph and routes it through a reservoir model. The applicable inflow design flood (IDF), starting conditions, and freeboard must be established for the project under ER 1110-8-2(FR) (USACE, 1991); EM 1110-2-1420 (USACE, 2018), Chapter 14, describes the spillway study framework.
HEC-HMS can be used to compute the PMF, using PMP depths as input for the hypothetical storm. Common loss and transform methods can be used, but adjustments to the parameters may be required to represent the worst-case condition. Likewise, dam and spillway performance can be simulated with the reservoir model included in HEC-HMS. For that, the analyst must derive and specify functions that describe how the reservoir will perform.
Key Takeaways
Key Steps in HEC-HMS
Configure the accepted extreme-event precipitation inputs using an appropriate method, such as a Hypothetical Storm with a user-defined pattern. Check storm duration, depth, timing, and the treatment of already-areal PMP inputs.
Check the loss and transform assumptions for extreme-event runoff. Evaluate the unit response when adjusting Clark parameters, and document any Variable Parameter Clark relationships.
Enter current reservoir storage and substantiated spillway/outlet discharge relationships. With Outflow Structures Routing, check crest elevations, lengths, coefficients, units, and vertical datum.
Run the required starting-pool and outlet-availability scenarios. Identify the assumptions in component names and document sensitivity to initial storage and operational reliability.
Compare inflow peak and volume, maximum routed pool elevation, outflow, and hydrograph duration. Check computational interval sensitivity and provide the results for the separate freeboard and dam-safety assessments.
Common Pitfalls
Inapplicable PMP inputs. Confirm regional coverage and project acceptance before selecting a PMP source or storm method. HMR 51 and HMR 52 have a specified eastern-US domain; EM 1110-2-1420 (USACE, 2018), paragraphs 7-3d and 7-3e, addresses regional and site-specific PMP.
Selecting storms by inflow peak alone. Reservoir storage and outflow respond to hydrograph timing and volume as well as peak flow. Route the candidate storms through the reservoir before identifying the critical pool elevation, and check the full duration of high water (EM 1110-2-1420 (USACE, 2018), paragraphs 14-4 and 14-5).
Assumed starting pool or outlet availability. Use the project's required antecedent and operating conditions, then test sensitivity. The historical spillway-crest starting pool and unavailable low-level outlets are not universal defaults (ER 1110-8-2(FR) (USACE, 1991), paragraphs 8c through 8f).
Unjustified response adjustments. Document changes to loss parameters and unit-hydrograph response, including the basis for any variable-parameter transform. Check the resulting response against the study assumptions and the peaking guidance in ER 1110-8-2(FR) (USACE, 1991), paragraph 8b.
Routed pool elevation treated as the freeboard assessment. HEC-HMS supplies the routed pool hydrograph; account separately for the applicable wave, wind, and other freeboard allowances. Use ER 1110-8-2(FR) (USACE, 1991), paragraph 9, and EM 1110-2-1420 (USACE, 2018), Chapter 15.